Where Charlestown's Hood Park Grocery and Hood Green Stand This Fall

The Boston Planning and Development Agency board approved the grocery store planned for Hood Park on December 11, 2025, almost a year ago. This month Hood Park is asking residents to write letters supporting the next phase, which it describes as "a new grocery store, a full acre of publicly accessible green space, and 132 new homes," and it says that approval would move the grocery forward along with the green and the housing. In the city's project records, the filing still under review is the building next door: the hotel-and-residential tower at 25 Supertest Street and the lawn that comes with it, Hood Green.

The two addresses depend on each other. The grocery building holds the affordable homes the tower is required to provide. The tower can't be occupied until the green is finished. For a resident following when there will be a second place to buy groceries, and a new place to sled, the two projects are steps in one sequence.

The Baseline at Bunker Hill Mall

Charlestown has one full-service grocery store, the Whole Foods Market at the Bunker Hill Mall, as the Boston Globe noted when the Hood Park store was approved. That storefront has a history. The mall opened with an A&P as its supermarket anchor, according to a 2015 Patriot-Bridge column looking back at the neighborhood's grocery history. Later the space was Johnny's Foodmaster. In late 2012, the Charlestown Patriot-Bridge reported that Foodmaster would close at the end of November and Whole Foods would take over the lease.

The city's neighborhood plan, PLAN: Charlestown, adopted by the BPDA board in 2023, described getting to groceries outside the neighborhood this way: under 15 minutes for drivers, and as long as 40 minutes for transit riders. It called for "an additional, more affordable grocery store." The Hood Park store is the city's answer to that recommendation.

15 Supertest Street, Approved in December 2025

Boston Planning's December 11, 2025 board summary lists the approved building at 15 Supertest Street this way:

  • Ground floor: a new grocery store, sized at 24,000 square feet in the Globe's account
  • Above it: 32 homes, 26 of them income-restricted
  • Jobs: about 52 construction jobs and about 34 permanent jobs
  • Building: all-electric, LEED Gold
  • Street-level extras: new landscaping and public realm improvements, $18,595 to the Boston Transportation Department for bikeshare, and more than $102,000 in mitigation funding

The Globe described it as a small-format grocery with its address on Rutherford Avenue: one level of store with two levels of mostly affordable apartments above. The grocer has not been named publicly. At the approval meeting, Mark Rosenshein of Trademark Partners, Hood Park's development consultant, laid out the order of construction: "We want to get the grocer and that affordable component done first."

Earlier in 2025, the developer gave an advisory group a schedule estimate. According to the Patriot-Bridge, the target was to start building 15 Supertest in the second quarter of 2026 and open it about 18 months after that. Those were the developer's projections from that time.

Why the Grocery Carries the Tower's Affordable Homes

The 26 income-restricted homes above the grocery "are being delivered early as part of the income-restricted unit requirement from the proposed 25 Supertest Street hotel and residential project."

In other words, the tower's affordable housing goes into the grocery building, and it gets built first. That explains why the grocery came before the bigger building, and why Hood Park presents the two as one package. The same December 11 vote approved a second amendment to the Hood Park master plan, which originally set aside only 12,000 square feet of retail at 15 Supertest when the BPDA approved it in 2019. The 2025 changes doubled that space and made it a grocery.

25 Supertest Street, the Piece Still Under Review

The tower is a separate filing. Boston Planning held a public meeting on June 22, 2026 for the Article 80 submission filed in May, and the comment period closed August 14. On October 6, the Boston Civic Design Commission had 25 Supertest and Hood Green on its agenda for final review and recommendation. Hood Park says the commission approved the designs that day and that the company wants Boston Planning Department approval by December 31, 2026, about six weeks after this post publishes.

15 Supertest Street 25 Supertest Street
What it is Grocery with homes above Hotel and residential tower with Hood Green
Homes 32, with 26 income-restricted 108 in the city's October 6, 2026 project record
Other uses Single-level store, about 24,000 sq ft 130 hotel keys
Height Three levels 18 levels, 235 feet per the design team
City status Approved by BPDA board December 11, 2025 In review, Hood Park seeking approval by December 31, 2026

At the June meeting, architect David Manfredi of Elkus Manfredi Architects described 104 apartments. In the Patriot-Bridge's account, each use gets its own core: "their own separate elevators, entrances, and front desks." Hood Park's November summary counts 132 homes across both buildings, including 20 affordable apartments with two, three and four bedrooms for households earning 60 percent of area median income.

The tower has gotten smaller. In June 2025, Universal Hub reported a proposal for 160 hotel rooms and 90 market-rate apartments. The current plan has 130 keys.

On timing, Rosenshein told June meeting attendees that permitting comes before financing, that he hoped to finish permitting by fall or early winter, and that the team expects to start construction in 2027.

Hood Green Opens With the Tower

Hood Park's November summary sets this order: Hood Green and the first segment of the Charlestown Green Loop are built with 25 Supertest, and both have to be ready for public use before the building gets its certificate of occupancy. Hood Park will build and maintain the acre, and it will stay free and open to the public.

The design is still being worked out. At the June meeting, Kate Kennon of Offshoots, the landscape architects, said her office is on Rutherford Avenue and that talks with the community about the green go back to 2018. The Patriot-Bridge recorded the ideas presented that night:

  • A flexible lawn in the center for sledding, a pickup soccer game or a movie night
  • A more naturalistic, adventure-style play area, different from the play structure at Ryan Playground
  • A multi-use plaza next to the lawn that could hold events and markets, like the programming already held along Hood Park Drive
  • "Great sun exposure," in Kennon's words

The team said a separate community meeting would focus on how the space gets used. Restrooms are already part of the discussion. A resident at the meeting asked for public facilities closer to the green and more than two single restrooms. Rosenshein said public restrooms are open on campus at 6 Stack, separate from the facilities for The Yard at Hood Park.

Where the Green Loop Goes Next

The green is also where the Charlestown Green Loop starts. PLAN: Charlestown proposed the loop as a neighborhood-wide walking and biking network of trails and greenways, and the final draft rerouted it to reach the Mystic River and follow the waterfront. The Hood Park master plan already calls for a bike and pedestrian path along the site's north edge, linking planned Rutherford Avenue paths to Spice Street and Sullivan Square station.

The board meeting that approved the grocery also moved two waterfront projects forward. It accepted a $500,000 MassTrails grant from the state Department of Conservation and Recreation and approved bidding for the Little Mystic Channel Harborwalk Extension, which fills in a missing piece of the Boston Harborwalk. It also gave Courageous Sailing tentative designation to redevelop Pier 5 in the Navy Yard. That plan includes a roof terrace, a harbor pool and floating dock, and an ecological learning lagoon.

The Sequence, in Order

  1. August 2025: At an advisory group meeting, the developer targets a second-quarter 2026 start for 15 Supertest and an opening about 18 months later.
  2. December 11, 2025: The BPDA board approves the 15 Supertest grocery and homes, along with the Hood Park master plan amendment.
  3. June 22, 2026: A public meeting is held on 25 Supertest and Hood Green, with comments open until August 14.
  4. October 6, 2026: The Boston Civic Design Commission does its final review of 25 Supertest and Hood Green.
  5. December 31, 2026: Hood Park's target date for Boston Planning Department approval of 25 Supertest.
  6. 2027: The developer's stated construction start for 25 Supertest. Hood Green has to open before the tower is occupied.

The Hood Park item in the Patriot-Bridge has a QR code residents can use to send letters to the Boston Planning Department and elected officials. Mark Rosenshein is the developer's representative, and Sarah Peck at the Boston Planning Department manages the Hood Park project.

If you're weighing how a grocery store and a new public green a short walk away might change a home near Rutherford Avenue or Sullivan Square, The McLaren Team tracks Hood Park's approvals closely. We'd be glad to go through what's planned within a few blocks of your address, whether you're staying put or getting ready to sell. See our Charlestown neighborhood page, or Start Your Move with a conversation.